Shut down activities for Wabamun power plant began in 2002 and are expected to continue until after 2010. The project schedule is as follows:
| Activity | Date Range |
| Decision to implement phased shut down, including immediate shut down of Unit 3 (139 MW) | Nov. 2002 |
| Unit 3 Alberta Energy & Utilities Board (AEUB) filing | Nov. 2003 |
| Environmental Site Assessment (ESA) | 2003 - 2005 |
| End of Wabamun Power Purchase Agreement (PPA) | Jan. 1, 2004 |
| Units 1 and 2 AEUB Filing | March 2004 |
| Ongoing stakeholder consultation (refer to Appendix A of 2005 Remediation and Reclamation plan) | 2004 + |
| Shut down of Units 1 (62 MW) and 2 (57 MW) | Dec. 31, 2004 |
| Wabamun remediation and reclamation plan submitted to Alberta Environment (AENV) | Dec. 2005 |
| Negotiated Settlement Agreement application filed with EUB for approval | Aug. 2006 |
| Application to AENV for Phase 1 of decommissioning | Oct. 2006 |
| EUB Decision 2006-129 Approval of Negotiated Settlement Agreement | Dec. 2006 |
| AENV approves phase one of the decommissioning project | April 2007 |
| Phase 1 and 2 asbestos removal on Units 1, 2 and 3 | 2006 - 2009 |
| Received AENV Approval amendment for east discharge location | March 2008 |
| Reclamation and ash removal (Phase 1) 70 per cent complete (APEC 5) | 2008-2009 |
| Submit application to AENV for final phase of decommissioning (post-shut down) | Sept. 2008 |
| Shut down Unit 4 | March 31, 2010 |
| Demolition of power plant building | 2010 + |
| Complete remediation and reclamation | 2010 + |
TransAlta submitted a detailed remediation and reclamation plan to Alberta Environment in December 2005, following extensive environmental research, stakeholder consultation and analysis. An executive summary of the plan can be downloaded from the Related Documents area of this page. The complete submission is available on CD.